CRL station taking shape below Auckland streets

Publish Date : 13 May 2021

Construction of New Zealand’s deepest railway station is celebrating a significant milestone with the project pouring the last concrete to complete the first underground floor ( B1 in pink below) of City Rail Link’s Karangahape Station.

CRL station taking shape below Auckland streets

The floor at the Mercury Lane entrance to the station is one of five that will carry people to and from the platforms 25 metres below ground.

“It’s great to see a station that’s going to have a huge impact on the Karangahape Road area slowly taking shape,” says Jonathan Hill, the Karangahape Station Manager for the Link Alliance.

“There’s been some pretty intense work in a confined central city area to complete the floor successfully.”

The excavation beneath the street level entrance floor and then the construction of the first underground floor has taken 10 weeks. Approximately 9000 cubic metres of material – enough to fill three Olympic-sized swimming pools - was first removed before 880 cubic metres of concrete was poured and some 280 tonnes of reinforcing steel fitted.

Deeper below ground, work on excavating the top heading of the first of the two 223-metre-long platform tunnels is almost complete, and at the station’s Beresford Square entrance preparations are underway to begin pouring the first underground ‘B1’ level of the station.

CRL station taking shape below Auckland streets (1)
The B1 slab cures under the roof of Karangahape Station

Work on the Karangahape Station began in late 2019 with the demolition of the old Mercury Plaza and adjacent buildings. The station structure is due to be completed by 2023 to be followed by the station fit-out - the installation of mechanical and electrical equipment that includes lighting, escalators, lifts, ventilation and communication systems.

The Link Alliance is delivering the stations, tunnels and rail systems contract for City Rail Link Ltd.

The $4.4 billion City Rail Link is the largest transport infrastructure project undertaken in New Zealand. It is planned to be completed in 2024 and Aucklanders will benefit from a transformed public transport network when it opens.

Stay up to date with the City Rail Link project at cityraillink.co.nz