$5m Paremoremo Road repair complete

Publish Date : 22 Nov 2024
380 Paremoremo Road slip (after)
Slip repair at 380 Paremoremo Road.
380 Paremoremo Road slip
Before the slip repair at 380 Paremoremo Road

An 11-month repair to four slip sites within a 3.7km stretch of Paremoremo Road on the North Shore is now complete.

The major slip damage was a result of the storm events in January and February 2023 and involved Fulton Hogan construction teams working sequentially to install three timber retaining walls collectively measuring 145m and a 52m concrete palisade wall.

Improved drainage facilities, footpaths and guardrails have been installed and reinstated ground areas hydroseeded.

Total four-slip repair cost: $5.26 million

More than 2000 slips were recorded across Auckland during the early 2023 storm events. 1200 slips were cleaned up quickly and by the end of October another 604 minor and major slips had been repaired.

Back to News